-
1964
- Proposal to AEC for 500 MeV Linac
-
1966
- Funding of 400 MeV Linac authorized (December 1966)
-
1967
- Middleton site acquired
- Start of construction authorized by AEC-New York Operations Office (April 1967)
- Begin: Building construction (September 1967). Beam switchyard design. Center-line waveguide design (to cope with beam blowup problem demonstrated at SLAC)
- Let: Contract for transmitters (Energy Systems, Inc.);Contract for accelerator RF peripherals (SLAC)
- Make decision to limit experimental program to electron scattering
-
1968
- Let contract for accelerator waveguide (Varian)
- Begin design details energy loss spectrometer, ELSSY
- Begin design details and specify water, vacuum, electrical systems design
- Pursue Litton switchtube difficulty and design change requirements
-
1969
- Building occupied. Begin utilities, vacuum, water systems installation
- Complete injector design and initial testing – MIT campus
-
1970
- Accelerator waveguide construction completed and delivered to site; begin accelerator assembly
- Prototype transmitter completed, delivered to site, assembled for acceptance testing
- Let contract for energy loss spectrometer work
- Demonstrated pre-injector pulsed beam performance (440 keV, 4000+ pps, > 50 milliamps peak, > 20 µsec)
-
1971
Transmitter prototype accepted
Begin assembly balance of transmitters; begin installation of beam switchyard
Let spectrometer hardware and power supply contracts (Lukens, Grumman, Bath Iron Works, Alpha)
Demonstrate injector 7.5 MeV beam and 100 MeV accelerated beam
-
1972
- Complete assembly of full linear accelerator centerline; mechanical, electrical assembly of RF transmitters; implementation of basic control system
- Complete basic beam transport system to straight-through 14° and Spectrometer Room beam ports
- Spectrometer power supply delivered and assembled
- Demonstrate 126 MeV accelerated beam (delta p/p = 0.2% for 80% of beam)
- Formal establishment of User’s Organization (first Chairman, H. Crannell)
-
1973
- Demonstrate 1% RF 48 hour endurance operation (170 MeV, 3 transmitter operation)
- Accelerator brought to 400 MeV capability in preparation for January 1974 demonstration
- 14° beam line implemented and installed first phase gamma-pi experiment
- Carried through horizontal assembly of energy loss high resolution spectrometer magnet and performed magnetic measurements
- Installation underway of spectrometer peripherals, electrical, water, vacuum systems: spectrometer carriage, focal plane array, target chamber, remaining vacuum systems, etc., under construction
- Dual PDP 11/45 computer data analysis system acquisition initiated
-
1974
- Brief, low duty ratio run of full accelerator, 5 transmitters, 406 MeV: ~ 1 µA beam current to 14° area
- Vertical assembly of high resolution spectrometer completed
- 100 hours of ~ 1 µA beam at 125 to 200 MeV energy delivered to first phase gamma-pi experiment
-
1975
- High resolution spectrometer operating in the “energy loss” mode achieved an unprecedented 1.1 x 10**-4 resolution
- First 16O(gamma, p) data obtained
-
1976
- Development of vertical drift chambers for the electron spectrometer completed. The new system represented a major advance in the instrumentation of spectrometer focal plane systems
- Construction completed on a fixed angle magnetic spectrometer in the 14° area for the study of the (gamma, pi±) reaction
-
1977
- 180° scattering facility installed and used for physics experiments
- Expansion of laboratory facilities authorized
- Fixed angle 250 MeV pi° detector for experiments in the 14° area
-
1978
- Large diameter beam dumping system installed at the high resolution electron scattering facility
-
1979
- South Hall and new buildings completed
- Authorization received to construct a beam recirculator to increase maximum beam energy from 410 MeV to 750 MeV
- Authorization received by Yale to design and build the polarized source for Bates
-
1980
- First electron beam put into the South Hall
-
1981
- Opening angle pi° spectrometer operational and taking data
-
1982
- Successful operation of the recirculator
- Completion of construction of the One Hundred Inch Proton Spectrometer (OHIPS) and the Medium Energy Pion Spectrometer (MEPS)
- First electron scattering and pion production experiments in the South Hall
- Detailed design of BigBite spectrometer started
-
1983
- Fabrication and installation of sixth RF transmitter begun. Rework of modulators 2 through 5 begun. These projects will increase maximum energy to 1060 MeV
- Extension of utility building begun
- First (e,e’p) experiment
-
1984
- Polarized source moved from Yale to Bates for completion
- TIRUS, a Bates-developed very high speed readout system, installed on MEPS
-
1985
- Completion of electron scattering experiments on tritium
- Completion of construction of the BigBite spectrometer
-
1986
- Delivery of polarized electrons for experiments
- High intensity pure photon beams available on Beam Line C
-
1987
- Deuteron tensor polarization experiment, 2H(e,e’d), with a high power liquid deuterium target
- Initiation of advanced accelerator R&D for a pulse stretcher ring
-
1988
- Begin construction of the South Hall Stretcher Ring (SHR) with commissioning scheduled for 1992
- Installation of the Moeller polarimeter on Beam Line B
- Completion of the 12C Parity Violation Experiment
-
1989
- Begin construction of first generation out-of-plane magnetic spectrometer system
-
1990
- First measurements of quasi-elastic spin response: 3He(e,e’)
- First measurement using out-of-plane spectrometer system to obtain longitudinal-transverse interference response functions
- Record high energy for an experiment (903 MeV), record high momentum transfer (42/fm**2), record low cross-section measurement (5 x 10**-40 cm**2/sr/MeV) for deuterium electrodisintegration at threshold
-
1991
- First measurement of fifth response function (C12 + deuteron), using polarized electrons and the out-of-plane spectrometer
- Measurement of neutron charge form factor, via spin transfer to the neutron, using the neutron polarimeter
-
1992
- Beam successfully injected into the new Injection Line and transported through the West Straight Section of the SHR
-
1993
- Beam stored in SHR on first day of storage commissioning. Operation with full-turn injection of 40 µA (design maximum) demonstrated
- Focal-plane proton polarimeter installed in OHIPS
- Energy compression system commissioned; factor of ten easily obtained
-
1994
- Demonstrated resonant extraction from SHR
- Began major upgrade program for linac and recirculator
-
1995
- SAMPLE experiment takes first data
-
1996
- BLAST funding approved
-
1997
- BLAST construction begins
- Measurement of 3He magnetic form-factor to high momentum transfer
- Ring commissioning demonstrates 5 minute lifetime of 60 mA stored current at 750 MeV
- High intensity and quality SAMPLE beam developed
-
1998
- Measurement of n -> Delta transition with OOPS in both pi° and pi+ channels
- SAMPLE data taking on Hydrogen
- First stored Beam in SHR on Internal target
-
1999
- Over 200 mA in South Hall Ring
- SAMPLE data taking on Deuterium
-
2000
- Completion and commissioning of OOPS spectrometer
- VCS experiment: uses high duty factor beam and full OOPS spectrometer
- SAMPLE results published in Science
- OOPS running with extracted unpolarized CW beam, energies from 570 to 670 MeV, currents up to 10 μA, extraction efficiency 80 to 94%
- 60 kV test setup for preparation and certification of polarized electron guns
- Compton Polarimeter installed in SHR; back-scattered photons detected
- Beam energy of 1 GeV achieved, with 14 mA peak current
-
2001
- OOPS running with extracted polarized CW beam, energy 950 MeV, current 10 μA, extraction efficiency 90%, duty factor 65%
- Stored polarized beam in the SHR using Siberian Snake; 670 MeV, 50 mA, 30 minute lifetime
- First observation of stored polarized electron beam spin flip using a prototype RF dipole
- Fiber-coupled diode laser installed in polarized source
-
2002
- Completion of SAMPLE running at 125 MeV on deuterium
- Completion of OOPS running
- BLAST assembly and magnetic field mapping
- Strained GaAs photocathode and diode laser used to produce highly polarized electron beam (>60%), stored in SHR; 850 MeV, 100 mA, 40 minute lifetime
- 98% efficient spin flip achieved using a second RF dipole
-
2003
- Installation of BLAST neutron detectors
- BLAST commissioning, with beam quality monitors used to optimize beam tune
- Compton Polarimeter commissioned for operation with beam currents above 200 mA
- Atomic Beam Source installed; first polarized internal target in the SHR
-
2004
- BLAST deuterium and hydrogen running. High target vector polarizations (>80%) achieved with installation of a collimator upstream of the target cell
- Low-momentum compaction lattice used in SHR to reduce bunch length to 3.6 ps
-
2005
- BLAST data taking optimized with a second-level trigger and front-end buffering
- Wire chamber and coincidence rates used to further improve beam tune. Beam lifetimes of 25 minutes with target gas achieved routinely
- BLAST deuterium running completed
- Coherent synchrotron radiation in SHR detected near 100 GHz
- MIT takes ownership of the Bates facility